
MORE PROJECTS
Pumping Station Refurbishments
Batch works for JN Bentley and ETM covering the whole of Yorkshire
This is an ongoing scheme throughout AMP5 which in total covers over 250 pumping stations, the work mostly consists of panel, pump and instrument changes to existing kiosks or pumping stations but in some case there are new.
Up to December 2013 we have completed approximately 190 of these refurbishments.


Harrogate South WwTW FFD Scheme
Laing O'Rourke scheme
This was our first large scheme tendered in November 2008 for Laing O'Rourke with an initial scheme value of £300k. We began work in February 2009 and was completed in October 2009, on time and within budget even after completing additional works which gave us a final scheme value of £360k
For a more detailed report and photo's please click
Spen Valley - Mitchell Laithes Phase 2
JN Bentley Scheme
The scheme covered 4 No. sites; Mitchell Laithes, Spenborough, Moorend and North Bierley, consisting of cable containment, SWA cabling, instrumentation, profibus, building services and external lighting / emergency lighting.
For a more detailed report and photo's please click


Sutton WwTW - FFD Scheme
Mott MacDonald Bentley Scheme
To meet Ammonia consent and to improve the water quality of the River Aire, the existing site had a new Inlet works, sewage pumps and washwater system installed.
The LV electrical installation was started in August 2013 and completed in May 2014